Location: Pradhikaran-Nigdi, Pimpri-Chinchwad — Gyan Prabhodni school, about 2,500 students
Timeline: April 2024 – January 2025, including a 7-day pop-up demonstration
Cost: ₹6 lakh pilot in permanent materials (thermoplastic, wayfinding, signage); ₹60–70 lakh planned for capital works
What was done
GDCI came to Pune through Bloomberg Philanthropies’ road safety initiative. Crash records, travel patterns, age profiles and walking and cycling routes formed the evidence base. A “reverse periscope” let parents see the street from a child’s 90 cm eye level. An on-street cycle route took students through four types of infrastructure, and children consistently chose the most protected one. The Municipal Commissioner and the Executive Engineer backed a trial converting the street to one-way, which cut speeding sharply.
What happened next
Only 8 residents came to the pre-trial meeting, but 350 attended the end-of-trial town hall demanding removal, mainly over parking and route changes. The city moved to a two-way design with narrower 5.5–6 m lanes, continuous footpaths and shaded seating, keeping most of the safety benefit.
Key lesson
Go door to door before a trial; an invitation to a meeting is not enough. Maintenance and street-works budgets can fund signage, markings and speed calming without a special capital allocation.