Location: Kharadi, Pune — a 24 m wide street with 5 schools within 1 km
Timeline: About 6 months from design to tactical trial (post-COVID); permanent works ongoing
Budget: Tactical trial at minimal cost. Permanent works for 1 km need ₹5 crore; ₹50 lakh sanctioned so far, for signage and zebra crossings only
What was done
Arkmira won a design competition that required a five-day tactical intervention on the ground before final working drawings. Schools, children, parents and neighbours took part rather than a contractor alone. Children painted road markings, schools hosted workshops, and a cycle rally showed how a protected cycle track would work. Working drawings for a one-kilometre transformation across five schools were completed after the trial.
Challenges
The civil budget for footpaths and cycle tracks has not been sanctioned; only ₹50 lakh for signage was released.
Frequent changes of executive officers at Pune Municipal Corporation reset institutional memory.
Implementation began when PMC had no elected representatives, removing a key source of pressure.
Outreach to the ward MLA and corporator is continuing.
Key lesson
Even without the full civil budget, the first 100 m outside a school gate can be transformed for ₹2–22 lakh through tactical measures alone , if the school, traffic police and bus operators are actively engaged.